Lemare Construction

Partnership

Boney Creek Development’s partnership with Lemare Construction is built on shared values of reliability, environmental stewardship, and Indigenous inclusion. Known for their technical expertise and proven results in remote and sensitive terrains, Lemare has been a trusted collaborator on critical infrastructure and habitat restoration projects across Northwest BC.

Lemare Group and Boney Creek Development working together on forestry and construction projects—supporting road upgrades and environmental work in Northwest British Columbia

Our Projects

Prince Rupert Gas Transmission Project (PRGTP)

The 2024 PRGT Road Upgrades project involved upgrading 18 km of resource roads, quarry development, and bridge installation in a 50-day construction window. Lemare’s scope included blasting and hauling 67,000m³ of aggregate from multiple quarries to support road improvements, all while working near fish-bearing streams and sensitive environmental features. The project was completed on time with zero safety or environmental incidents, maintaining a minimum of 30% local and Indigenous workforce. Lemare’s strong relationship with the Nisga’a Nation and reputation for efficient execution were key factors in meeting the project’s “Substantial Started” designation.

18 km Resource Road Upgrades

Water Management & Culvert Installation

60,000 m³ Road Aggregate Material Blasted & Hauled

 700 LM of Sheet Pile Wall

7000 m³ of riprap developed for bridge installation

Glacier Creek Fish Habitat Offset Project

The Glacier Creek Fish Habitat Offset Project (GCFHOP) included a 17ha site with 6 new ponds to be constructed, along with interconnecting channels and an outlet channel connecting to the Bell-Irving-River. This site had approximately 150,000m³ of material to be excavated. The majority of excavations were up to 6m below the ground water table elevations, making this a challenging opportunity.

BCLJV implemented complex dewatering systems, along with sheet piling to execute this scope successfully. Large volumes of imported material were required from local sources for spawning gravels, riprap and other fish habitat features. This project was completed in the summer of 2023 and marked a major milestone for the KSM project. The project risks had to be managed carefully, as the location is in close proximity to the Bell-Irving-River. The quantity of water being released from site could have had major impacts on this environmentally sensitive area, and Lemare Qualified Environmental Professionals monitored and managed these aspects diligently.

> 100 Million Gallons of Water Pumped & Discharged

 170,000m² of Habitat Creation

 150,000m³ Excavated Material

 40,000m³ 100-year Flood Berm Construction

Project Highlights

Glacier Creek Fish Habitat Offset Project

Lemare and Boney Creek Development crews working on PRGT road improvements—hauling aggregate and supporting pipeline infrastructure in remote regions of Northwest British Columbia
  • Dewatering complexities in areas where excavations were >6m below water table elevation.

  • Site reclamation upon scope completion to plant native trees, shrubs, grasses and mulch production, and placement on topsoil covered areas.

Prince Rupert Gas Transmission Project (PRGTP)

Sheet pile shoring installation for Glacier Creek Fish Habitat Offset Project—Lemare and Boney Creek Development restoring aquatic habitat in glacial terrain
Completed excavation and dewatering work for Glacier Creek Offset Pond—environmental mitigation project led by Boney Creek Development and Lemare Group in Northwest British Columbia
  • Major milestone for PRGTP to complete early works and achieve “substantially started” designation

  • Expedited timeline and successful execution of blasting and hauling >67,000 m³ of blast rock in 50 days